KEENE, N.H. (MyKeeneNow.com) Several construction, infrastructure and maintenance projects are planned across Keene during Thanksgiving week, including work that will temporarily affect traffic, parking and access to public spaces.
The city’s Public Works Department has outlined work scheduled for the week of Nov. 22, with projects ranging from sewer and water improvements to tree removal and ongoing park renovations.
At Central Square, Casella Construction will continue sewer utility work Monday, Nov. 23, in the square and along Main Street near Davis Street. Parking spaces and portions of the square within the work zone may be temporarily closed or shifted, with detours in place. Traffic patterns and parking are expected to return to normal at the end of each business day.
Work will also continue at the George Street Bridge, where New England Infrastructure will complete installation of a gabion wall along the stream bank and perform site cleanup beginning Monday. The bridge and George Street are scheduled to reopen to traffic Wednesday, Nov. 25. Additional cleanup is expected to continue through Dec. 6, ahead of the seasonal construction shutdown. Final paving, vegetation restoration and sidewalk installation are planned for spring 2027.
On Elm Street, Gordon’s Property Maintenance Services will resume installation of a new water main between Timberlane Drive and Drummer Hill Road at 8 a.m. Monday. Traffic will be restricted to alternating one-way travel in active work areas as needed. The work is expected to continue through Wednesday, Nov. 25, with normal traffic operations restored by the end of the day.
Tree work will affect Maple Avenue and Wheelock Park on Wednesday, Nov. 25. Phil’s Tree Service, working under contract with the city, will remove up to 20 red pine trees at Wheelock Park that Parks and Recreation staff have identified as being in poor condition and requiring removal to help maintain a safe environment for visitors.
Most of the work will take place near the park entrance, between the walkway and driveway. Several additional trees will be removed near the Newman Street slip lanes.
The tree removal is limited to those specifically identified by city staff and is not a park-wide effort. Access to the park will be restricted while crews are actively working. The work is scheduled to begin at 8 a.m. and is expected to be completed that day. Maple Avenue will also be closed and detoured during the operation.
Elsewhere, construction will begin Monday on the Monadnock View Cemetery expansion project off Park Avenue. Park Construction Corp. is scheduled to start work at 7 a.m. Sections of the cemetery undergoing construction will be closed to visitors both during and outside working hours. Work is expected to continue through Wednesday, with crews finishing their activities each day at the close of business.
At Robin Hood Park, Weston & Sampson CMR will begin installing drains as part of the pool rehabilitation project at 9 a.m. Monday. The public will not have access to active construction areas or the parking lot sections being used for staging. The pool and affected parking areas will remain closed until the project is finished. Work is expected to continue through Wednesday.
The city asks residents and visitors to plan accordingly, follow posted detours and traffic controls, and use caution around construction crews and equipment.